Top Menu

Progress Made on Dunkin’ Donuts Park

Hartford Yard Goats

Weeks after construction resumed at Dunkin’ Donuts Park, planners are confident that the ballpark will be ready for the Hartford Yard Goats (Class AA; Eastern League) 2017 season.

After taking over the project, Arch Insurance tabbed Whiting-Turner to finish the ballpark, which was to have opened for the 2016 season but was hit with a myriad of delays. Construction was halted in June when the contract for developers Centerplan Construction Co. and DoNo Hartford was terminated by the city.

Whiting-Turner assumed work on the project in October, with the goal being to have Dunkin’ Donuts Park ready by the Yard Goats’ home opener on April 13. According to project officials, that timeline appears to be realistic, as Whiting-Turner is not only making progress on previously uncompleted tasks, but is also shoring up other areas of the facility. More from The Hartford Courant:

“We are making significant progress, and we’re still on track for baseball in April 2017,” said Patrick Nails, a senior vice president with Arch Insurance, which is guaranteeing the completion of Dunkin’ Donuts Park in time for the season opener.

Nails said that there are usually 70 to 80 contractors on site daily, six days a week.

The ballpark has been winterized to keep pipes from bursting once the weather turns. The heating and electrical systems are nearing completion, as is work on the guardrails in the stands.

One elevator is fully operational; a second is almost there. The home team locker room has been completed and awaits a finish coat of paint, as do several luxury suites. Many areas of the ballpark have already received a fresh coat of paint. Much of the construction debris that was left behind in June is gone.

Progress is reportedly being made on other aspects of Dunkin’ Donuts Park, including the Yard Goats’ offices, the 360-degree concourse, and repairs to the roof.

RELATED STORIES: Dunkin’ Donuts Park Part of Lawsuit Between Arch, CenterplanConstruction Resumes at Dunkin’ Donuts Park; Centerplan Documents Dunkin’ Donuts Park; Work May ResumeCenterplan Files Suit to Prevent Dunkin’ Donut Park Construction Work; Work to Resume Next Week on Dunkin’ Donuts Park; Developer Sued by Contractor in Hartford; Arch to Takeover Dunkin’ Donuts Park CompletionAudit Shows Rising Costs in HartfordMcEachern to Hartford: Finish the Ballpark!Hartford Mayor: No Thanks to Solomon’s Financial Offer; Yard Goats Release 2017 Sched; Solomon Offers to Pay for Ballpark Work; IFG: Over 180 Issues With Dunkin’ Donuts Park;Contractor: We Could Resume Hartford Ballpark in September; Work Set to Resume on New Hartford BallparkYard Goats Bring up Possibility of Leaving Hartford; Dunkin’ Donuts Park Will Not Open for 2016 SeasonFinally: Dunkin’ Donuts Park Spat Ends Up in CourtHartford, Team May Finish New Yard Goats Ballpark; Hartford Rejects Settlement Offer; Hartford Developer Pitches Ballpark Completion Plan; Fire Watch Unfolding at Dunkin’ Donuts ParkYard Goats Lay Off Four in Wake of Ballpark BreakdownNew Hartford Ballpark Now Insured; Hartford Ballpark Uninsurable After Developer Booted; Centerplan CEO: City Recklessly Terminated Contract; Yard Goats to Play Two Home Series in Binghamton; Tensions, Schedule Changes in Hartford; Hartford Stadium Authority Cancels Contract with Developer; When Will Hartford Ballpark Be Done? No One is Saying; Legal Issues Could Prevent Hartford Ballpark Opening This Season; New Deadline Targeted for Dunkin’ Donuts Park; Officials: New Hartford Ballpark Could Open Next Month; Hartford: We Doubt New Ballpark Will Open on Time; Dunkin’ Donuts Park Facing Potential Delay; New Hartford ballpark set for May 31 opening; Yard Goats to begin 2016 season on the road; Solomon: “Awful, depressing, disconcerting” ballpark situation; New Hartford ballpark opening delayed at least a month; New Hartford ballpark cost estimate: $10.3 million over budget; City: New Hartford ballpark may open late; Value engineering underway in Hartford

 

, , ,